McLaren Construction Midlands and North to deliver Plot 4 of landmark industrial hub in Bristol

McLaren Construction Midlands and North has been appointed to deliver Plot 4 of the transformative Matrix 49 industrial scheme in Avonmouth, Bristol, on behalf of Equation Properties Ltd.

Works on Plot 4 commenced in February this year, with a forecasted programme of 66 weeks to deliver completion by April 2026.

Early works are set to include ground improvements and piling works, alongside the installation of a new foul pumping station, and the programme will see the design and construction of a 596,000 sq. ft speculative warehouse unit, accompanied by office space, transport hubs, a link bridge, and a gatehouse.

The project also includes external works, underground drainage, utility connections, and landscaping, contributing further to the site’s evolution into a prime logistics and industrial hub.

Aligning with McLaren Construction’s commitment to sustainability, the scheme is aiming to achieve a BREEAM Excellent rating and will adhere to the Considerate Constructors Scheme and Smart Waste BRE standards. Once complete, the development will provide new employment opportunities and long-term economic benefits to the local community.

McLaren’s partnership with Equation Properties has been instrumental in driving the phased transformation of Matrix 49, Plot 3, a £21.6 million development spanning 13 acres. Plot 3 is currently on track to deliver a 219,660 sq. ft warehouse and 11,365 sq. ft of office space. Nearing completion, the phase showcases McLaren’s capability to manage complex site conditions, including rhine diversions and ground level improvements, while protecting local ecology.

Gary Cramp, managing director of McLaren Construction Midlands and North, said: “Our continued work with Equation Properties reflects our dedication to delivering high-quality, sustainable industrial spaces. Plot 4 builds upon the success of Plot 3, contributing further to the development of this strategic site in Avonmouth. This phase presents exciting opportunities to enhance local employment while meeting the evolving needs of future tenants striving towards net zero targets.”